BAYLANDS BATTERY
250 MW storage in San Mateo, CA · In queue since April 2021 · Proposed COD March 2030
250 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
8y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-03-24
The Baylands Battery project is a proposed 250 MW battery storage project located in San Mateo County, California. The project is interconnected to the CAISO grid under queue ID CAISO-1900, with Pacific Gas & Electric (PGAE) as the utility. The project entered the interconnection queue on April 15, 2021, and has a proposed commercial operation date of March 24, 2030. Its interconnection status is currently in the System Impact Study phase.
The Baylands Battery project is being tracked due to its appearance in recent industry news.
Generated from interconnection queue and public data sources
State
CA
County
San Mateo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Martin 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- DALYCTY_1_N005
- POI Substation
- Martin Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.