ZORIN STORAGE
252 MW storage in Alameda, CA · In queue since April 2021 · Proposed COD February 2034
252 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2034
Total Duration
12y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2034-02-19
The ZORIN STORAGE project is a proposed 252 MW battery energy storage system located in Alameda County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1911, with a queue entry date of April 15, 2021. Pacific Gas and Electric (PGAE) is the utility.
The proposed commercial operation date for the ZORIN STORAGE project is February 19, 2034. The project's interconnection status is currently in the System Impact Study phase. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
CA
County
Alameda
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Newark 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- NEWARKD_1_N001
- POI Substation
- Newark Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about ZORIN STORAGE