SUNBEAM STORAGE
100.9 MW storage in San Mateo, CA · In queue since April 2021 · Proposed COD February 2034
100.9 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2034
Total Duration
12y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2034-02-19
The Sunbeam Storage project is a proposed 100.9 MW battery energy storage system located in San Mateo County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1919, with a queue entry date of April 15, 2021. Pacific Gas & Electric (PGAE) is the utility. The proposed commercial operation date is February 19, 2034, and the project's interconnection status is currently in the System Impact Study phase.
The project consists of 100.9 MW of battery storage. The point of interconnection is Cooley Landing 60 kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
San Mateo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Cooley Landing 60 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- BLLEHVN_6_N002
- POI Substation
- Cooley Landing Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about SUNBEAM STORAGE