APACHE STORAGE
203.699 MW storage in Fresno, CA · In queue since April 2021 · Proposed COD May 2029
203.699 MW
Capacity
1
Components
Battery
5y 1m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2029-05-21
The APACHE STORAGE project is a proposed 203.7 MW battery storage project located in Fresno County, California. The project is interconnected to the PG&E utility and is listed in the CAISO interconnection queue as queue ID CAISO-1930, with an entry date of April 15, 2021. The proposed commercial operation date is May 21, 2029, and the interconnection agreement has been executed.
The APACHE STORAGE project has been the subject of recent news coverage, with at least nine articles published regarding the project. These articles cover topics such as deals, regulatory matters, and industry news.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Sanger 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SANGER_1_N001
- POI Substation
- Sanger Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14