APACHE STORAGE (CAISO-1930) — Project Summary

Queue ID
CAISO-1930
Capacity
203.699 MW
Technology
Battery
Status
active
Location
Fresno, CA
Region
CAISO
Developer
IA Status
IA Executed

APACHE STORAGE

CAISO-1930BetaActiveBatteryCAISOLBNL + Live

203.699 MW storage in Fresno, CA · In queue since April 2021 · Proposed COD May 2029

203.699 MW

Capacity

1

Components

Battery

5y 1m

In Queue

IA Executed

IA Status

COD target: 2029

Status
Latest milestoneCOD achievedEnergy-Storage.News · 2025-08-20
Interconnection

Total Duration

8y 1m

Construction75%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2029-05-21

About

The APACHE STORAGE project is a proposed 203.7 MW battery storage project located in Fresno County, California. The project is interconnected to the PG&E utility and is listed in the CAISO interconnection queue as queue ID CAISO-1930, with an entry date of April 15, 2021. The proposed commercial operation date is May 21, 2029, and the interconnection agreement has been executed.

The APACHE STORAGE project has been the subject of recent news coverage, with at least nine articles published regarding the project. These articles cover topics such as deals, regulatory matters, and industry news.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Fresno

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

PGAE

Entity

CAISO

Service Type

Point of Interconnection

Sanger 115 kV

Data Source

LBNL + Live

DeveloperNational Renewable Solutions±Energy-Storage.News · 2025-08-20
EPC contractorGridworksEnergy-Storage.News · 2025-08-20
ApplicantJuniper Spring Solar, LLCWhite Mountain Independent · 2025-12-18
AgencyApache County Board of SupervisorsWhite Mountain Independent · 2025-12-18
RulingApprovalWhite Mountain Independent · 2025-12-18
TransactionProject financingEnergy-Storage.News · 2025-07-03
Deal value$155.0MEnergy-Storage.News · 2025-07-03
LenderSociete GeneraleEnergy-Storage.News · 2025-07-03
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
SANGER_1_N001
POI Substation
Sanger Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (3)Beta

Last updated 2026-03-14