PUMA STORAGE
203.699 MW storage in Madera, CA · In queue since April 2021 · Proposed COD November 2030
203.699 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
9y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-11-18
The PUMA STORAGE project is a proposed 203.7 MW battery energy storage system located in Madera County, California. The project is in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-1933. Its queue entry date is April 15, 2021, and the proposed commercial operation date is November 18, 2030. The project's interconnection status is currently in the System Impact Study phase.
The project is being developed within the Pacific Gas and Electric (PGAE) service territory. The point of interconnection (POI) is the Borden 230 kV substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Madera
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Borden 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.