LOTUS SOLAR 2
406.4 MW hybrid in Madera, CA · In queue since April 2021 · Proposed COD November 2030
406.4 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
9y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-11-17
The LOTUS SOLAR 2 project is a proposed 406.4 MW hybrid solar and battery energy storage project in Madera County, California. The development project consists of 203.2 MW of solar photovoltaic generation paired with 203.2 MW of battery storage. It is located within the California Independent System Operator (CAISO) region and is interconnected to the PG&E utility grid at the Borden 230 kV point of interconnection.
The project, identified as CAISO-1934 in the CAISO interconnection queue, entered the queue on April 15, 2021. Its proposed commercial operation date is November 17, 2030. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
CA
County
Madera
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Borden 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about LOTUS SOLAR 2