ELYSIAN
412.182 MW hybrid in Fresno, CA · In queue since April 2021 · Proposed COD October 2029
412.182 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-10-18
ELYSIAN is a proposed 412.18 MW hybrid solar and battery energy storage project located in Fresno County, California. The development project consists of 206.09 MW of solar photovoltaic generation paired with 206.09 MW of battery storage. It is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-1935, with an interconnection queue entry date of April 15, 2021. The project's proposed commercial operation date is October 18, 2029, and its interconnection agreement has been executed. The point of interconnection is the Tranquility 230 kV substation.
The project, which is in the Pacific Gas & Electric (PGAE) service area, has been featured in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Tranquility 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about ELYSIAN