WINGTIP SOLAR 1
2,352.2 MW hybrid in Merced, CA · In queue since April 2021 · Proposed COD September 2032
2,352.2 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
11y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-09-18
WINGTIP SOLAR 1 is a proposed solar and battery hybrid project located in Merced County, California. The development project has a total capacity of 2352.2 MW, consisting of 1176.1 MW of solar generation and 1176.1 MW of battery energy storage.
The project is in the CAISO interconnection queue (queue ID CAISO-1943) with an entry date of April 15, 2021. The proposed commercial operation date is September 18, 2032. The project's interconnection status is currently in the System Impact Study phase. The point of interconnection is the Los Banos 500 kV substation.
Generated from interconnection queue and public data sources
State
CA
County
Merced
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Los Banos 500 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SNTANLA_6_N001
- POI Substation
- Los Banos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.