FLORES STORAGE
151.742 MW storage in Madera, CA · In queue since April 2021 · Proposed COD February 2031
151.742 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-18
The FLORES STORAGE project is a proposed 151.74 MW battery storage project located in Madera County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-1953, with a queue entry date of April 15, 2021. The proposed commercial operation date is February 18, 2031. The project's interconnection status is currently in the System Impact Study phase.
The project, which will interconnect to the PG&E grid at the Gregg 230 kV point of interconnection, is being tracked by industry news sources, with three recent articles covering the development.
Generated from interconnection queue and public data sources
State
CA
County
Madera
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Gregg 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about FLORES STORAGE