CIERVO MOUNTAIN HYBRID
254.94 MW hybrid in Fresno, CA · In queue since April 2021 · Proposed COD August 2029
254.94 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 4m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-08-03
The proposed CIERVO MOUNTAIN HYBRID project is a 254.94 MW solar and battery energy storage hybrid project located in Fresno County, California. The project consists of a 127.57 MW solar component and a 127.37 MW battery energy storage component.
The project is in the CAISO interconnection queue as queue ID CAISO-1955, with a queue entry date of April 15, 2021. The proposed commercial operation date is August 3, 2029. The interconnection agreement has been executed. The point of interconnection is the Excelsior 115 kV substation.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Excelsior 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.