TARRAGON HYBRID
71.93 MW hybrid in Fresno, CA · In queue since April 2021 · Proposed COD June 2028
71.93 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The TARRAGON HYBRID project is a proposed 71.93 MW hybrid solar and battery energy storage project located in Fresno County, California. The development project, consisting of 35.98 MW of solar generation and 35.95 MW of battery storage, is interconnected to the PG&E utility network.
The project is listed in the CAISO interconnection queue under queue ID CAISO-1975, with an entry date of April 15, 2021. The proposed commercial operation date is June 1, 2028. The project's interconnection status is currently in the System Impact Study phase, and it will connect to the grid at the Crescent 70 kV point of interconnection.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Crescent 70 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about TARRAGON HYBRID