ARTEMIS
824.672 MW hybrid in Kern, CA · In queue since April 2021 · Proposed COD October 2029
824.672 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-18
The ARTEMIS project is a proposed 824.67 MW hybrid solar and battery energy storage project located in Kern County, California. The development project consists of 412.34 MW of solar generation paired with 412.34 MW of battery storage. The project is interconnected to the CAISO grid at the Arco 230 kV point of interconnection.
The ARTEMIS project is listed in the CAISO interconnection queue as entry CAISO-1980, with a queue entry date of April 15, 2021. The proposed commercial operation date is October 18, 2029. The project's interconnection status is currently in the System Impact Study phase. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Arco 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- AGRICO_7_B1
- POI Substation
- Agrico
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.