EIGER ENERGY STORAGE
100.9 MW storage in Kern, CA · In queue since April 2021 · Proposed COD February 2032
100.9 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
10y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-02-16
The EIGER ENERGY STORAGE project is a proposed 100.9 MW battery storage project located in Kern County, California. Interconnection is requested through the CAISO queue, with queue ID CAISO-1994. The project entered the queue on April 15, 2021, and has a proposed commercial operation date of February 16, 2032. The project's interconnection status is currently in the System Impact Study phase, and it is requesting interconnection to the PG&E grid at the Lamont 115 kV point of interconnection.
The development project consists solely of battery storage, with a total capacity of 100.9 MW. It is currently listed as an active project within the CAISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Lamont 115 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.