SERENA STORAGE
114.264 MW storage in Kern, CA · In queue since April 2021 · Proposed COD September 2029
114.264 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
8y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-18
The SERENA STORAGE project is a proposed 114.26 MW battery energy storage system located in Kern County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2001, with a queue entry date of April 15, 2021. The proposed commercial operation date is September 18, 2029. The project's interconnection status is currently in the System Impact Study phase.
The project, which is being developed within the Pacific Gas and Electric (PGAE) service area, has been mentioned in recent news coverage related to regulatory and development matters. The point of interconnection is the Kern PP 230 kV substation.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Kern PP 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about SERENA STORAGE