CHERRY LANE HYBRID
621.26 MW hybrid in Kern, CA · In queue since April 2021 · Proposed COD June 2031
621.26 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
10y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-19
The CHERRY LANE HYBRID project is a proposed 621.26 MW hybrid solar and battery energy storage development in Kern County, California. The project consists of 310.63 MW of solar photovoltaic generation paired with 310.63 MW of battery storage. It is located within the CAISO region and interconnects to the grid at the Wheeler Ridge 230 kV point of interconnection.
The project is listed in the CAISO interconnection queue as CAISO-2015, with a queue entry date of April 15, 2021. The proposed commercial operation date is June 19, 2031. Its interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Wheeler Ridge 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WHEELER_6_N001
- POI Substation
- Wheeler Ridge Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.