TROLLEY
405.663 MW storage in San Bernardino, CA · In queue since April 2021 · Proposed COD February 2031
405.663 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-26
The TROLLEY project is a proposed 405.66 MW battery storage project located in San Bernardino County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2032, with a queue entry date of April 15, 2021. The proposed commercial operation date is February 26, 2031. The project's interconnection status is currently in the System Impact Study phase.
The project, which will interconnect to Southern California Edison (SCE) at the Etiwanda Substation 230 kV, has been mentioned in recent industry news.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Etiwanda Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.