CARMINE
360.296 MW storage in Riverside, CA · In queue since April 2021 · Proposed COD May 2031
360.296 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
10y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-05-01
The CARMINE project is a proposed 360.3 MW battery storage project located in Riverside County, California. The project is being developed within the California Independent System Operator (CAISO) region and is interconnected with Southern California Edison (SCE). It entered the CAISO queue as queue ID CAISO-2033 on April 15, 2021, with a proposed commercial operation date of May 1, 2031.
Currently, the project's interconnection status is in the System Impact Study phase. The point of interconnection (POI) is the Colorado River Substation 230 kV. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Colorado River Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CRIMSN_7_CN3
- POI Substation
- Colorado River Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CARMINE