ELION ENERGY STORAGE
302.4 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD May 2034
302.4 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2034
Total Duration
13y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2034-05-26
The Elion Energy Storage project is a proposed 302.4 MW battery storage project located in Los Angeles County, California. Interconnection is being sought through the CAISO queue, with queue ID CAISO-2064. The project entered the queue on April 15, 2021, and has a proposed commercial operation date of May 26, 2034. Its interconnection status is currently in the System Impact Study phase.
The project is interconnected with Southern California Edison (SCE) at the Antelope Valley Substation 230 kV point of interconnection. Recent news coverage indicates activity related to the project, with five articles appearing, primarily focused on deals and grid-related topics.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Antelope ValleySubstation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about ELION ENERGY STORAGE