DRIFTER ENERGY STORAGE (CAISO-2066) — Project Summary

Queue ID
CAISO-2066
Capacity
504.8 MW
Technology
Battery
Status
active
Location
Ventura, CA
Region
CAISO
Developer
IA Status
System Impact Study

DRIFTER ENERGY STORAGE

CAISO-2066BetaActiveBatteryCAISOLBNL + Live

504.8 MW storage in Ventura, CA · In queue since April 2021 · Proposed COD March 2033

504.8 MW

Capacity

1

Components

Battery

5y 1m

In Queue

System Impact Study

IA Status

COD target: 2033

Interconnection

Total Duration

11y 11m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2033-03-26

About

The DRIFTER ENERGY STORAGE project is a proposed 504.8 MW battery storage project located in Ventura County, California. The project is interconnected to the CAISO grid via the Moorpark Substation at 230 kV and is in the CAISO interconnection queue as entry CAISO-2066, with a queue entry date of April 15, 2021. The proposed commercial operation date is March 26, 2033, and the project's interconnection status is currently in the System Impact Study phase.

The DRIFTER ENERGY STORAGE project is proposed by an unknown developer and connects to Southern California Edison (SCE). The project has been the subject of recent news coverage, with four articles categorized as industry, regulatory, and grid-related.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Ventura

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SCE

Entity

CAISO

Service Type

Point of Interconnection

Moorpark Substation 230 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
MOORPARK_6_N005
POI Substation
Moorpark Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.