BOBOR STORAGE (CAISO-2068) — Project Summary

Queue ID
CAISO-2068
Capacity
152.1 MW
Technology
Battery
Status
active
Location
Tulare, CA
Region
CAISO
Developer
IA Status
System Impact Study

BOBOR STORAGE

CAISO-2068BetaActiveBatteryCAISOLBNL + Live

152.1 MW storage in Tulare, CA · In queue since April 2021 · Proposed COD December 2030

152.1 MW

Capacity

1

Components

Battery

5y 1m

In Queue

System Impact Study

IA Status

COD target: 2030

Interconnection

Total Duration

9y 8m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-26

About

The BOBOR STORAGE project is a proposed 152.1 MW battery energy storage system located in Tulare County, California. The project is in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2068. The queue entry date is April 15, 2021, and the proposed commercial operation date is December 26, 2030. The project's interconnection status is currently in the System Impact Study phase and will connect to the Rector Substation at 230 kV.

The project is being developed within the Southern California Edison (SCE) service territory. Recent news coverage has discussed the development of energy storage projects in California, including projects similar to BOBOR STORAGE.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Tulare

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SCE

Entity

CAISO

Service Type

Point of Interconnection

Rector Substation 230 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_ZP26_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
RECTOR_6_N009
POI Substation
Rector Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about BOBOR STORAGE