SOLEIL CANTIL
597.3 MW hybrid in Kern, CA · In queue since April 2021 · Proposed COD February 2033
597.3 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2033
Total Duration
11y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-02-26
The SOLEIL CANTIL project is a proposed 597.3 MW hybrid solar and battery energy storage project located in Kern County, California. The development project, consisting of 372.3 MW of solar capacity and 225 MW of battery storage, is interconnected to the CAISO grid at the Windhub Substation 500kV.
The project is listed in the CAISO interconnection queue as queue ID CAISO-2078, with an entry date of April 15, 2021. The proposed commercial operation date is February 26, 2033. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
CA
County
Kern
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Windhub Substation 500kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ALTA6B2_7_N003
- POI Substation
- Windhub Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.