SOLSKEN
809.42 MW hybrid in Tulare, CA · In queue since April 2021 · Proposed COD February 2033
809.42 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2033
Total Duration
11y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-02-26
The SOLSKEN project is a proposed solar and battery energy storage hybrid project located in Tulare County, California. The development project, with a total capacity of 809.42 MW, consists of a 464.42 MW solar component and a 345 MW battery energy storage system. It is located within the CAISO region and is being developed for Southern California Edison (SCE).
The project is listed in the CAISO interconnection queue as entry CAISO-2085, with an interconnection queue entry date of April 15, 2021. The proposed commercial operation date is February 26, 2033. Its interconnection status is currently in the System Impact Study phase, and the point of interconnection is the Springville Substation at 230 kV.
Generated from interconnection queue and public data sources
State
CA
County
Tulare
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Springville Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- SPRINGVL_6_N006
- POI Substation
- Springville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.