CONDUIT ENERGY STORAGE
512.58 MW storage in San Bernardino, CA · In queue since April 2021 · Proposed COD February 2031
512.58 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
9y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-02-26
The CONDUIT ENERGY STORAGE project is a proposed 512.58 MW battery storage project located in San Bernardino County, California. The project is interconnected to the CAISO grid via the Lugo Substation 500 kV. It entered the CAISO interconnection queue as queue ID CAISO-2105 on April 15, 2021, with a proposed commercial operation date of February 26, 2031. Its interconnection status is currently in the System Impact Study phase.
The development project is listed in the CAISO interconnection queue and has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Lugo Substation 500 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Lugo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CONDUIT ENERGY STORAGE