GABRIEL STORAGE
405.751 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD May 2033
405.751 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2033
Total Duration
12y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2033-05-15
The Gabriel Storage project is a proposed 405.75 MW battery energy storage system located in Los Angeles County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2113, with a queue entry date of April 15, 2021. The proposed commercial operation date is May 15, 2033. The project's interconnection status is currently in the System Impact Study phase.
The project, which is interconnected with Southern California Edison (SCE), has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Rio Hondo Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- RIOHONDO_6_N004
- POI Substation
- Rio Hondo Substation