CORAL REEF
405.663 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD April 2032
405.663 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
11 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-04-26
The proposed CORAL REEF project is a 405.66 MW battery storage development in Los Angeles County, California. It is located within the CAISO region and is interconnected with Southern California Edison (SCE). The project entered the CAISO queue as queue ID CAISO-2117 on April 15, 2021, and has a proposed commercial operation date of April 26, 2032. Its interconnection status is currently in the System Impact Study phase.
The project consists entirely of battery storage, with a total capacity of 405.66 MW. The point of interconnection (POI) is the El Nido Substation 230 kV. The CORAL REEF project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
El Nido Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ELNIDBIO_6_N001
- POI Substation
- Sjve El Nido
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CORAL REEF