GREENWOOD ENERGY STORAGE
252 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD May 2032
252 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
11y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-05-26
The Greenwood Energy Storage project is a proposed 252 MW battery storage project located in Los Angeles County, California. The project is in the California Independent System Operator (CAISO) interconnection queue, identified as CAISO-2121, with an interconnection queue entry date of April 15, 2021. The proposed commercial operation date is May 26, 2032. The project's interconnection status is currently in the System Impact Study phase and will connect to the Mesa Substation at 500 kV.
The development project is listed in the CAISO queue under Southern California Edison (SCE). Greenwood Energy Storage has been the subject of recent news coverage, with nine articles categorized as industry, regulatory, and deals related.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Mesa Substation 500 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- MESACAL_6_N004
- POI Substation
- Mesa Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about GREENWOOD ENERGY STORAGE