TABLA ENERGY STORAGE
302.4 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD May 2032
302.4 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
11y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-05-26
The TABLA ENERGY STORAGE project is a proposed 302.4 MW battery energy storage system located in Los Angeles County, California. The project is in the California Independent System Operator (CAISO) interconnection queue under queue ID CAISO-2124. Its queue entry date is April 15, 2021, and the proposed commercial operation date is May 26, 2032. The project's interconnection status is currently in the System Impact Study phase.
The project, which will interconnect to Southern California Edison (SCE) at the Rio Hondo Substation 230 kV point of interconnection, has appeared in recent news coverage regarding energy storage development in California.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Rio Hondo Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- RIOHONDO_6_N004
- POI Substation
- Rio Hondo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about TABLA ENERGY STORAGE