TYRELL ENERGY STORAGE
302.4 MW storage in Orange, CA · In queue since April 2021 · Proposed COD May 2032
302.4 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
11y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-05-26
The proposed TYRELL ENERGY STORAGE project is a 302.4 MW battery storage development in Orange County, California. It is located within the CAISO region and is interconnected with Southern California Edison (SCE) at the Viejo Substation 230kV.
The project is listed in the CAISO interconnection queue as queue ID CAISO-2125, with an entry date of April 15, 2021. Its proposed commercial operation date is May 26, 2032. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
CA
County
Orange
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Viejo Substation 230kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- VIEJOSC_2_N004
- POI Substation
- Viejo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.