LOS NIETOS
102.26 MW storage in Orange, CA · In queue since April 2021 · Proposed COD April 2031
102.26 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
10 years
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-04-26
The Los Nietos project is a proposed 102.26 MW battery storage project located in Orange County, California. The project is interconnected to Southern California Edison (SCE) and is in the California Independent System Operator (CAISO) queue as entry CAISO-2129, with a queue entry date of April 15, 2021. The proposed commercial operation date is April 26, 2031.
The project's interconnection status is currently in the System Impact Study phase. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
CA
County
Orange
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Johanna Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- JOHANNA_2_N007
- POI Substation
- Johanna Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about LOS NIETOS