MERLIN STORAGE
200 MW storage in Los Angeles, CA · In queue since April 2021 · Proposed COD May 2032
200 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2032
Total Duration
11y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2032-05-26
The MERLIN STORAGE project is a proposed 200 MW battery energy storage system located in Los Angeles County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2131, with a queue entry date of April 15, 2021. Southern California Edison (SCE) is the utility. The proposed commercial operation date is May 26, 2032, and the project's interconnection status is currently in the System Impact Study phase.
The project, being developed within the CAISO region, consists solely of battery storage, with a total capacity of 200 MW. The point of interconnection (POI) is the Hinson Substation at 220 kV.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
Hinson Substation 220 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HINSON_2_B1
- POI Substation
- Hinson Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.