DELAMAR ENERGY STORAGE 2
256.29 MW storage in Clark, NV · In queue since April 2021 · Proposed COD June 2027
256.29 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-26
The proposed DELAMAR ENERGY STORAGE 2 project is a 256.29 MW battery storage development in Clark County, Nevada. It is located within the California Independent System Operator (CAISO) region and is interconnected to the SCE portion of Eldorado Substation at 230 kV. The project entered the CAISO queue as queue ID CAISO-2141 on April 15, 2021.
The project's interconnection status is currently in the System Impact Study phase, with a proposed commercial operation date of June 26, 2027. Recent news coverage has discussed the project.
Generated from interconnection queue and public data sources
State
NV
County
Clark
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
SCE portion of Eldorado Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about DELAMAR ENERGY STORAGE 2