ROCK VALLEY ENERGY CENTER
1,023.64 MW hybrid in Nye, NV · In queue since April 2021 · Proposed COD March 2029
1,023.64 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
7y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-03-15
The Rock Valley Energy Center is a proposed hybrid solar and battery project located in Nye County, Nevada. The development project has a total capacity of 1023.64 MW, consisting of 508.56 MW of solar generation and 515.08 MW of battery energy storage.
The project is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-2144, with an entry date of April 15, 2021. The proposed commercial operation date is March 15, 2029, and the Interconnection Agreement (IA) has been executed. The point of interconnection is the Beatty Substation at 230 kV.
Generated from interconnection queue and public data sources
State
NV
County
Nye
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
—
Point of Interconnection
Beatty Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_NP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.