SUNBAKED SOLAR
1,023.64 MW hybrid in Inyo, CA · In queue since April 2021 · Proposed COD February 2029
1,023.64 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
7y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-02-26
The proposed SUNBAKED SOLAR project is a 1023.64 MW hybrid solar and battery energy storage development in Inyo County, California. The project consists of a 508.56 MW solar array coupled with a 515.08 MW battery energy storage system. It is located within the CAISO region and is interconnected to the Trout Canyon Substation at 230 kV.
SUNBAKED SOLAR entered the CAISO interconnection queue as queue ID CAISO-2149 on April 15, 2021, with a proposed commercial operation date of February 26, 2029. The project's interconnection agreement has been executed. The transmission provider is GLW.
Generated from interconnection queue and public data sources
State
CA
County
Inyo
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
GLW
Entity
CAISO
Service Type
—
Point of Interconnection
Trout Canyon Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CANYONP4_7_GN001
- POI Substation
- Canyon
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.