ALISA SOLAR ENERGY COMPLEX
416.988 MW hybrid in Yuma, AZ · In queue since April 2021 · Proposed COD June 2028
416.988 MW
Capacity
2
Components
Solar + Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
7y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
The ALISA SOLAR ENERGY COMPLEX is a proposed hybrid solar and battery project located in Yuma County, Arizona. The development project has a total capacity of 416.99 MW, consisting of 208.49 MW of solar generation and 208.49 MW of battery energy storage. The project, which appeared in recent industry news, is interconnected to the CAISO grid under queue ID CAISO-2161, with a queue entry date of April 15, 2021.
The proposed commercial operation date for the ALISA SOLAR ENERGY COMPLEX is June 1, 2028. The project's interconnection point is at the Hoodoo Wash - North Gila 500 kV substation, and the interconnecting utility is SDGE. The project's interconnection status is currently in the System Impact Study phase.
Generated from interconnection queue and public data sources
State
AZ
County
Yuma
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
Hoodoo Wash - North Gila 500 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about ALISA SOLAR ENERGY COMPLEX