YUHA DESERT BATTERY STORAGE
633.1 MW storage in Imperial, CA · In queue since April 2021 · Proposed COD November 2031
633.1 MW
Capacity
1
Components
Battery
5y 1m
In Queue
System Impact Study
IA Status
COD target: 2031
Total Duration
10y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-11-05
The proposed YUHA DESERT BATTERY STORAGE project is a 633.1 MW battery storage development in Imperial County, California. Interconnection for the project is being managed through the CAISO queue, with queue ID CAISO-2176. The project entered the queue on April 15, 2021, and has a proposed commercial operation date of November 5, 2031. The interconnection status is currently in the System Impact Study phase.
The project is located within the San Diego Gas & Electric (SDGE) service territory and proposes to interconnect at the Imperial Valley Substation 230 kV. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
CA
County
Imperial
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
Imperial Valley Substation 230 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WESCAN_7_N002
- POI Substation
- Imperial Valley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.