BELL BLUFF STORAGE (CAISO-2178) — Project Summary

Queue ID
CAISO-2178
Capacity
312.96 MW
Technology
Battery
Status
active
Location
San Diego, CA
Region
CAISO
Developer
IA Status
System Impact Study

BELL BLUFF STORAGE

CAISO-2178BetaActiveBatteryCAISOLBNL + Live

312.96 MW storage in San Diego, CA · In queue since April 2021 · Proposed COD March 2035

312.96 MW

Capacity

1

Components

Battery

5y 1m

In Queue

System Impact Study

IA Status

COD target: 2035

Interconnection

Total Duration

13y 11m

Impact Study25%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)Current

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2035-03-05

About

The Bell Bluff Storage project is a proposed 312.96 MW battery energy storage system located in San Diego County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-2178, with a queue entry date of April 15, 2021. The proposed commercial operation date is March 5, 2035. The project's interconnection status is currently in the System Impact Study phase.

The project is being proposed for interconnection to the San Diego Gas & Electric (SDGE) grid at the Suncrest Substation 230 kV point of interconnection. Recent news coverage has discussed the development of the Bell Bluff Storage project.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

San Diego

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SDGE

Entity

CAISO

Service Type

Point of Interconnection

Suncrest Substation 230 kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
POI Substation
Suncrest Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about BELL BLUFF STORAGE