TOWNSHIP EXPANSION
22.6 MW hybrid in Sutter, CA · In queue since October 2022 · Proposed COD June 2024
22.6 MW
Capacity
2
Components
Gas + Battery
3y 7m
In Queue
Feasibility Study
IA Status
COD target: 2024
Total Duration
1y 8m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
The Township Expansion project is a proposed 22.6 MW hybrid development in Sutter County, California. Interconnecting within the CAISO queue as entry CAISO-2195 on October 13, 2022, the project consists of an 11.3 MW gas-fired component and an 11.3 MW battery energy storage system. The proposed commercial operation date is June 1, 2024.
The project's interconnection to PG&E is currently in the Feasibility Study phase, with the point of interconnection at the Greenleaf #1 115 kV Tap. The project is listed as active in the CAISO interconnection queue.
Generated from interconnection queue and public data sources
State
CA
County
Sutter
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Greenleaf #1 115 kV Tap
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.