TULE WIND
193.8 MW generation in San Diego, CA · In queue since May 2004 · Proposed COD October 2030
193.8 MW
Capacity
1
Components
Wind
22 years
In Queue
IA Executed
IA Status
Signed Mar 2011
Queue → IA
6y 10m
IA → COD
19y 7m
Total Duration
6y 10m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2030-10-31
The TULE WIND project is a proposed wind generation project with a total capacity of 193.8 MW, located in San Diego County, California. The project is interconnected to the CAISO grid via the Boulevard East Substation 138 kV and is in the CAISO interconnection queue as entry CAISO-32, with a queue entry date of May 24, 2004. The proposed commercial operation date is October 31, 2030. An Interconnection Agreement (IA) was executed on March 23, 2011.
The project is under development by an unknown developer and has been featured in recent news coverage. The utility is SDGE, and the interconnecting entity is CAISO.
Generated from interconnection queue and public data sources
State
CA
County
San Diego
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
Boulevard East Substation 138 kV
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Boulevard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14