ROSAMOND WEST SOLAR (CAISO-506) — Project Summary

Queue ID
CAISO-506
Capacity
447.3 MW
Technology
Solar+Battery
Status
active
Location
Kern, CA
Region
CAISO
Developer
IA Status
IA Executed

ROSAMOND WEST SOLAR

CAISO-506BetaActiveSolarBatteryCAISOLBNL + Live

447.3 MW hybrid in Kern, CA · In queue since July 2009 · Proposed COD March 2029

447.3 MW

Capacity

2

Components

Solar + Battery

16y 10m

In Queue

IA Executed

IA Status

Signed Aug 2020

Interconnection

Queue → IA

11y 1m

IA → COD

8y 7m

Total Duration

11y 1m

Construction75%
Queue EntryJul 31, 2009

Interconnection request submitted to ISO/RTO

Cluster Study (Phase I/II)

CAISO uses cluster studies where projects are batched annually and studied together.

Typical: 36–48 months (IR to IA)

Interconnection AgreementAug 5, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2029-03-31

Technology
Solar299.6 MW · 67%
Battery147.7 MW · 33%
About

The Rosamond West Solar project is a proposed 447.3 MW hybrid solar and battery energy storage project located in Kern County, California. The development project consists of a 299.6 MW solar photovoltaic array coupled with a 147.7 MW battery energy storage system. The project is interconnected to Southern California Edison (SCE) and is in the California Independent System Operator (CAISO) interconnection queue as queue ID CAISO-506, with an original queue entry date of July 31, 2009.

The proposed commercial operation date is March 31, 2029. An Interconnection Agreement (IA) has been executed for the project on August 5, 2020. The point of interconnection (POI) is the Whirlwind Substation at 230kV. The Rosamond West Solar project has been the subject of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

CA

County

Kern

Grid Region

CAISO (California)

Market

ISO/RTO Member

Developer

Utility

SCE

Entity

CAISO

Service Type

Point of Interconnection

Whirlwind Substation 230kV

Data Source

LBNL + Live

ApplicantHydrostorTehachapi News · 2025-06-24
AgencyCalifornia Energy CommissionTehachapi News · 2025-06-24
RulingApprovalTehachapi News · 2025-06-24
Market Context
Approximate
ISO / RTO
CAISO
Trading Hub
TH_SP15_GEN-APND
Hub Confidence
MEDIUM
Nearest Node (Estimated)
ASTORIA2_7_N001
POI Substation
Whirlwind Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.