CROW CREEK SOLAR 1 (FKA: FRONTIER SOLAR 1) (FKA AS SCATEC WESTSIDE SOLAR RANCH I AND STANISLAUS PV - PHASE 1)
40 MW hybrid in Stanislaus, CA · In queue since December 2009 · Proposed COD April 2025
40 MW
Capacity
2
Components
Solar + Battery
16y 5m
In Queue
IA Executed
IA Status
Signed Jul 2011
Queue → IA
1y 7m
IA → COD
13y 9m
Total Duration
1y 7m
Schedule
13 months past proposed COD
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-04-01
The Crow Creek Solar 1 (FKA: Frontier Solar 1) (FKA as Scatec Westside Solar Ranch I and Stanislaus PV - Phase 1) development project is a proposed 40 MW hybrid solar and battery energy storage system located in Stanislaus County, California. The project consists of 20 MW of solar generation paired with 20 MW of battery storage. It is listed in the CAISO interconnection queue as queue ID CAISO-539.
The project entered the CAISO queue on December 18, 2009, and has a proposed commercial operation date of April 1, 2025. An Interconnection Agreement (IA) for the project was executed on July 1, 2011. The point of interconnection is the Salado-Newman #1 60kV Line.
Generated from interconnection queue and public data sources
State
CA
County
Stanislaus
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
Salado-Newman #1 60kV Line
Data Source
LBNL + Live
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about CROW CREEK SOLAR 1 (FKA: FRONTIER SOLAR 1) (FKA AS SCATEC WESTSIDE SOLAR RANCH I AND STANISLAUS PV - PHASE 1)