RIGHTEOUS ENERGY STORAGE
500 MW storage in San Bernardino, CA · In queue since April 2023 · Proposed COD May 2030
500 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-05-27
Righteous Energy Storage is a proposed 500 MW battery energy storage project located in San Bernardino County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54501, with a queue entry date of April 17, 2023, and a proposed commercial operation date of May 27, 2030. The project's interconnection agreement (IA) status is "Not Started." Southern California Edison (SCE) is the utility. The point of interconnection (POI) is the Lugo 500 kV substation.
The Righteous Energy Storage project has been mentioned in recent news articles related to deals and regulatory matters.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
LUGO 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Lugo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.