Almond Wood Energy
153.034 MW generation in Kings, CA · In queue since April 2023 · Proposed COD December 2030
153.034 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2030
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
Almond Wood Energy is a proposed solar generation project with a total capacity of 153.03 MW. The project is located in Kings County, California, and is interconnected within the CAISO region. The project, which appeared in recent industry news, entered the CAISO interconnection queue as queue ID CAISO-54503 on April 17, 2023.
The proposed commercial operation date for Almond Wood Energy is December 31, 2030. As of the current data, the interconnection agreement status is "Not Started". The project's point of interconnection (POI) is the HENRIETTA 230 kV substation.
Generated from interconnection queue and public data sources
State
CA
County
Kings
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
HENRIETTA 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- HENRITTA_6_LN001
- POI Substation
- Henrietta Substation