Esteli Energy Storage
350 MW storage in Los Angeles, CA · In queue since April 2023 · Proposed COD May 2028
350 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-26
The Esteli Energy Storage project is a proposed 350 MW battery storage project located in Los Angeles County, California. Interconnection request CAISO-54507 was entered into the CAISO queue on April 17, 2023, with a proposed commercial operation date of May 26, 2028. The project's interconnection agreement status is listed as "Not Started." The project's point of interconnection is the OLINDA 230 kV substation, and Southern California Edison (SCE) is the utility.
The development project consists solely of battery storage, with a total capacity of 350 MW. The project is currently listed as "active" within the CAISO interconnection queue. The developer is not specified in the available data. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
OLINDA 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OLINDA_6_N001
- POI Substation
- Olinda Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.