Boulevardier
199 MW storage in San Diego, CA · In queue since April 2023 · Proposed COD March 2028
199 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
The Boulevardier project is a proposed 199 MW battery storage project located in San Diego County, California. The project is being developed within the California Independent System Operator (CAISO) region and is interconnected with San Diego Gas & Electric (SDGE) at the Boulevard East 138 kV point of interconnection.
The project entered the CAISO interconnection queue as queue ID CAISO-54508 on April 17, 2023. The proposed commercial operation date is March 31, 2028, and the interconnection agreement status is currently "Not Started". The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
CA
County
San Diego
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SDGE
Entity
CAISO
Service Type
—
Point of Interconnection
BOULEVARD EAST 138 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Boulevard
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Boulevardier