Broadview
1,294.64 MW hybrid in Fresno, CA · In queue since April 2023 · Proposed COD September 2028
1,294.64 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-01
The Broadview project is a proposed 1294.64 MW hybrid solar and battery energy storage development in Fresno County, California. The project consists of 810.16 MW of solar photovoltaic generation and 484.48 MW of battery storage. The project, which is in the California Independent System Operator (CAISO) interconnection queue as CAISO-54518, entered the queue on April 17, 2023, with a proposed commercial operation date of September 1, 2028. The interconnection agreement (IA) status is listed as "Not Started." The point of interconnection is the Los Banos-Gates #3 substation (PGAE Portion Only).
The Broadview project has been the subject of recent news coverage, with seven articles categorized as regulatory and industry news.
Generated from interconnection queue and public data sources
State
CA
County
Fresno
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
LOS BANOS-GATES #3 (PGAE Portion Only)
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articles