Duran
600 MW hybrid in San Bernardino, CA · In queue since April 2023 · Proposed COD March 2028
600 MW
Capacity
2
Components
Gas + Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-03-31
The Duran project is a proposed 600 MW hybrid development in San Bernardino County, California. The project, which consists of 300 MW of gas generation and 300 MW of battery storage, is located within the CAISO region and connected to the SCE utility.
The project is listed in the CAISO interconnection queue as CAISO-54526, with an entry date of April 17, 2023, and a proposed commercial operation date of March 31, 2028. As of the latest data, the interconnection agreement has not yet been started. The point of interconnection is the LUGO 500 kV substation. The Duran project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
San Bernardino
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
LUGO 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- POI Substation
- Lugo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Duran