Rover
206.2 MW storage in Los Angeles, CA · In queue since April 2023 · Proposed COD June 2028
206.2 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Rover is a proposed 206.2 MW battery storage project located in Los Angeles County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54531, with a queue entry date of April 17, 2023. Southern California Edison (SCE) is the utility. The proposed commercial operation date is June 30, 2028, and the interconnection agreement status is "Not Started".
The Rover project is being developed within the CAISO region. It consists of 206.2 MW of battery storage capacity. The point of interconnection is the VINCENT 230 kV substation. The project has been mentioned in recent news articles related to industry and regulatory matters.
Generated from interconnection queue and public data sources
State
CA
County
Los Angeles
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
VINCENT 230 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- VINCENT_2_N101
- POI Substation
- Vincent Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo ask pi reports yet for this entity.
ask pi about Rover