Calypso Solar 2
407.817 MW generation in Riverside, CA · In queue since April 2023 · Proposed COD October 2028
407.817 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
The Calypso Solar 2 project is a proposed 407.82 MW solar generation project located in Riverside County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54565, with a queue entry date of April 17, 2023. Southern California Edison (SCE) is the utility. The proposed commercial operation date is October 1, 2028, and the interconnection agreement (IA) status is "Not Started".
The project is located within the CAISO region and consists of 407.82 MW of solar photovoltaic generation. The point of interconnection (POI) is the COLORADO RIVER 500 kV substation. The developer is not specified in the queue data. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
COLORADO RIVER 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- CRIMSN_7_CN3
- POI Substation
- Colorado River Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Calypso Solar 2