Lycan Solar 2
192.491 MW generation in Riverside, CA · In queue since April 2023 · Proposed COD October 2028
192.491 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Not Started
IA Status
COD target: 2028
Total Duration
5y 6m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
Lycan Solar 2 is a proposed 192.49 MW solar generation project located in Riverside County, California. The development project, under review in the CAISO interconnection queue (CAISO-54567), is slated to connect to the RED BLUFF 500 kV point of interconnection via Southern California Edison (SCE). The project entered the queue on April 17, 2023, with a proposed commercial operation date of October 1, 2028. As of the latest data, the interconnection agreement (IA) has not yet been started.
The Lycan Solar 2 project has been the subject of recent news coverage, with 10 articles published across industry, grid, and development categories.
Generated from interconnection queue and public data sources
State
CA
County
Riverside
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
SCE
Entity
CAISO
Service Type
—
Point of Interconnection
RED BLUFF 500 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_SP15_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- OBERON_7_N122
- POI Substation
- Red Bluff Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Lycan Solar 2