Peach Storage
103.68 MW storage in Stanislaus, CA · In queue since April 2023 · Proposed COD November 2031
103.68 MW
Capacity
1
Components
Battery
3y 1m
In Queue
Not Started
IA Status
COD target: 2031
Total Duration
8y 7m
Interconnection request submitted to ISO/RTO
CAISO uses cluster studies where projects are batched annually and studied together.
Typical: 36–48 months (IR to IA)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-11-01
The Peach Storage project is a proposed 103.68 MW battery energy storage system located in Stanislaus County, California. The project is in the California Independent System Operator (CAISO) interconnection queue as entry CAISO-54584, with a queue entry date of April 17, 2023. Pacific Gas & Electric (PGAE) is the utility. The proposed commercial operation date is November 1, 2031, and the interconnection agreement status is "Not Started."
The project consists of 103.68 MW of battery storage. The point of interconnection is PIERCY 115 kV. The project is currently listed as "active" in the CAISO queue.
Generated from interconnection queue and public data sources
State
CA
County
Stanislaus
Grid Region
CAISO (California)
Market
ISO/RTO Member
Developer
—
Utility
PGAE
Entity
CAISO
Service Type
—
Point of Interconnection
PIERCY 115 kV
Data Source
LBNL
- ISO / RTO
- CAISO
- Trading Hub
- TH_ZP26_GEN-APND
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LECEFGT1_7_B1
- POI Substation
- Piercy Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.